Thanks mainly to the recent spell of good weather, progress has been good.




The roof is finished on the study extension, the front elevation and most of the rear.







The sunroom roof windows will be fitted next week and the roofing can then be completed.













Most of the stud walls on the first floor are now in place and a lot of the ground floor ceilings have had the plasterboard fitted

Most of the first fix plumbing has also been completed